Construction Planning

Project and Risk Management

Assignment Title – Construction Planning

NETWORK PROGRAMME FOR A BRIDGE PROJECT

A concrete bridge is to be constructed for a motorway project and the following activities, durations and sequences of work have been established.

An elevation and section of the proposed bridge is indicated in Fig 1.

Activity Duration

Site strip – complete bridge

Pier A

Excavate pier

Blinding to pier

Fix reinforcement & formwork to kicker

Concrete pier foundation

Reinforcement to abutment

Fix formwork

Concrete abutment

Strip Formwork

Deck slab (piers A to B)

Fix precast concrete beams

Fix formwork to deck

Fabricate and fix reinforcement

Concrete deck

Strip formwork to deck

Curing period prior to striking formwork 4 days

3 days

1 day

3 days **

1 day

4 days

5 days

1 day

2 days

**repeat activities on deck between piers B and C

1 day

5 days **

3 days

1 day

2 days

7 days

** repeat activities on deck between piers B and C

Resources to be allocated – Case 1

The following resources of temporary works and plant are to be allocated for the bridge construction.

One hydraulic excavator

One pier shutter

One set of formwork for the deck span between the piers.

An assessment is required of the minimum construction period for the bridge project based on the above resources.

Alternative considerations

Make suggestions for reducing the contract period by means of increasing resources for the project.

.

NOTE:- Produce a network diagram for the project utilising activity-on –arrow or precedence methods.

Last Updated on February 11, 2019