Microsoft Project

The Microsoft Tutorials are highly recommended to help you create a Microsoft Project Schedule for your Personal Project Schedule

 

 

  • Create a MS Project Schedule fictitious
  • In your main post, describe your project and how you decided on tasks and relationships.
  • The schedule needs to have at least 30 tasks in Project and have at least 10 relationships between tasks.  A relationship is a link between tasks (i.e. predecessors).  In addition, you should have at least 5 summary tasks. You also need to have 4 milestones.

Personal Project Schedule Rubric

 No Points Earned50% CreditFull Credit
Number of tasks0 Tasks15 Tasks30 Tasks
Relationships0 Relationships5 Relationships10 Relationships
Summary TasksSummary tasks not created2 Summary tasks created5 Summary tasks created
Milestones0 Milestones Created2 Milestones Created4 Milestones Created

 

Some students using the trial version of Microsoft Project have experienced a problem saving the assignment.  One solution that has been used with success is to place the curser in the Gantt portion of the screen and try again.

 