Computing Product Costs Using Activity-Based Costing:

Petrov Company identified the following activities, estimated costs for each activity, and identified cost drivers for each activity for this coming year. (These are the first three steps of the activity-based costing model).

ActivityCost DriverEstimated Annual Overhead CostsEstimated Annual Cost Driver Activity
Production setupNumber of production runs$ 60,000100 production runs
Materials handlingYards of material purchased140,00010,000 yards purchased
Quality controlNumber of inspections80,000800 inspections
Total$280,000

The company produces two products, MX1 and MX2. Information about these products of the month of March follows:

MX1MX2
Direct materials cost per unit$20$30
Direct labor costs per unit$15$45
Overhead cost per unit??
Product cost per unit??
Units produced1,000 units700 units

Actual cost driver activity levels for the month of March are as follows:

MX1MX2
Number of production runs36
Yards of materials purchased550230
Number of inspections4010

Required:

  1. Using the estimates for the year, compute the predetermined overhead rate for each activity (this is step 4 of the activity-based costing process).
  2. Using the activity rates calculated in requirement a and the actual cost driver activity levels shown for March, allocate overhead to the three products for the month of March (this is step 5 of the activity-based costing process).

Template for part (a)

ActivityCost DriverEstimated Overhead CostsEstimated Cost Driver ActivityPre-determined Overhead Rate
Production setupsNumber of production units$ [__________][____] runs$[____] per production run
Materials handlingYards of materials purchased$ [__________][____] yards$[____] per yard purchased
Quality controlNumber of inspections$ [__________][____] inspections$[____] per inspection
Total$ [__________]

Template for part (b)

MX1MX2
Pre-determined

Overhead Rate

Cost Driver ActivityOverhead AllocatedCost Driver ActivityOverhead Allocated
$[____] per production run[___]$ [__________][___]$ [__________]
$[____] per yard purchased[___]$ [__________][___]$ [__________]
$[____] per inspection[___]$ [__________][___]$ [__________]
Total allocated